Increased Duration

R

Raja

Hi,

I increased the duration of a completed task and published the task. but
still that Assignment in the Time Sheet doesn't show up in the "Current Task"
View it only shows in the "All Task View". Is There any way to make the
assignment appear in the "Current Task" View without affecting the actuals
for that task?
 
G

Gary L. Chefetz [MVP]

Raja:

Increasing duration of a "completed task" doesn't necessarily make it a
"current task." First, the task must not be *complete*, and second, it must
have open work assigned to a resource that was previously due, currently
due, or due to be worked on in the next N days where 'N' is the value you
set through administration.
 
Top