J
Joe M
I am a new Project 2003 user. Since I work against a finite number of hours
estimated into a job, I define the tasks as "Fixed Work". When I create three
tasks , enter the Work hours in each of the lower two, and then indent them
to the topmost (Summary) task, the Duration in the Sumamry Task is correct,
but the Work hours are double what I expect to see.
estimated into a job, I define the tasks as "Fixed Work". When I create three
tasks , enter the Work hours in each of the lower two, and then indent them
to the topmost (Summary) task, the Duration in the Sumamry Task is correct,
but the Work hours are double what I expect to see.