Indicator Column

M

Michelle

In professional the indicator column places a check next
to tasks that are considered 100% complete. In PWA it
doesn't look like the check mark is visible. Is there a
way to turn this on or another column that will provide
this check?

Thanks!
Michelle
 
D

Dale Howard [MVP]

Michelle --

In PWA, the Indicators column in a detailed Project view shows whether the
task has Risks, Issues, or Documents associated with it. It does not show
the checkmark indicator, however. If you really needed to see the checkmark
indicator, your organization could use a custom enterprise Task flag field
with a formula and graphical indicators. Hope this helps.
 