Indicator message for a Resource

L

Lars Westphal

Hi,
I I schedule one resouce to a tak in my project plan i have following
indicator message: "This resource shouldbe leveled based on a Day by Day
setting.
Could anyone pls. explain me what to do and how to change it.
Thanks Lars
 
J

JulieD

Hi Lars

don't you just love that message :)

basically Project is telling you that the resource is overallocated ... ie
has too much to do on one day ... this could come from a number of reasons
....
1) you have assigned more units of the resource than you have (you've got
100% Max Availability, but you've assigned 200% to a task)
2) you have assigned the resource to more than one task on a day which makes
his working hours on that day more than his available hours on that day (ie
you've assigned him to a 5hr task and a 6hr task, on the same day, but he
only works 8hrs)
3) you've assigned him to more than one task on the same day which do not
exceed his available hours but as they are scheduled to happen at the same
time Project classes the resource as overallocated.

The message itself says to "level the resource based on a day by day
setting" ... this means to use the resource levelling tool (tools / level
resource) to reschedule his work so that he is not overallocated.

this is often a good idea BUT first, check to see where / what the problem
is - i use resource allocation view for this (view / resource allocation -
apply) and filter so that only overallocated resources are showing and then
i have a look at each one to determine what's going on.... then i SAVE then
i will use the resource levelling tool ... to see the effect of resource
levelling - use the Levelling Gantt view (oh, and have a backup copy of your
project just in case).

also check out
www.tinyurl.com/2xbhc
for a series of project tutorials written by Mike Glen - he addresses
resource levelling in lesson 5 and 19.
 
F

Fei

thanks JulieD this response also helped me :)

just suggest that the message should be modified in next version saying:

"the resource is overallocated on one or more particular days, therefore
this resource should be leveled based on a Day by Day setting"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top