Individual task reporting as percentage not by hours

K

Kirsten

Is there a way to configure Project Server to have individuals report on
their task by percentage, not by hours? But I would like to be able to see
both.

Thank you for all you help
Kirsten
 
A

Andrew Lavinsky

Check Server Settings > Task Settings to toggle between the three methods of
reporting. Optionally, you could set a standard, or allow the PMs to change
by project (which I've never seen done).

You can display both.
 