G
Gerald Murphy
Good morning,
I am currently ready to baseline a project that is
scheduled for the next four years. As such our work
estimates are only valid for the work that will be
completed during the first year of construction and will
in turn be inflated each successive year. The inflation
percentage is unknown at this point and as such I am
unable to utilize the cost rate table to reflect
respective increases. Under the contract we are able to
claim inflation so I am wondering: Is there is a way to
reflect inflation for each successive year? (after the
project has been baselined)
Thanks for now
Gerald Murphy
I am currently ready to baseline a project that is
scheduled for the next four years. As such our work
estimates are only valid for the work that will be
completed during the first year of construction and will
in turn be inflated each successive year. The inflation
percentage is unknown at this point and as such I am
unable to utilize the cost rate table to reflect
respective increases. Under the contract we are able to
claim inflation so I am wondering: Is there is a way to
reflect inflation for each successive year? (after the
project has been baselined)
Thanks for now
Gerald Murphy