infrequent updates

K

kglynn

I'm in a situation where my job only allows me to get
into Project about once a month (!) to update with our
progress on multiple projects and determine if our
quarterly goals are realistic. I'm not a Project
Manager, that's just one of my job duties. When I
finally get into Project and go to adjust dates to bring
them up to speed with our actual schedule, I end up
adjusting all task dates of the project manually. Any
suggestions on how to make this process easier? Seems
like any task in the past is immovable and I don't know
what else to do but delete those tasks. Would be useful
to keep all old project information for future use.

thanks
 
M

Mike Glen

Hi kglynn,

Welcome to this Microsoft Project newsgroup :)

Try Tools/Tracking/Update project.../Reschedule uncompleted tasks to start
after:

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 