Inserted Projects (subprojects) In A Master Schedule

A

Allen

When I open a master schedule with multiple projects inserted, I can change
the 'Status Date' under project information and then update the project to
the new date via 'Tools, Tracking, Update Project'. The inserted projects
seem to calculate correctly if you check them independently, but the Status
Date is not changed. I.e., the Status Date entered for the master project is
not carried down to the subprojects. With all the data calulated correctly,
I end up opening subprojects ONLY to update the Status Date. Is this an
"oops" or done intentionally by design?
 