K
KT
Hi,
I am trying to find out the option of linking Microsoft Project and Excel. I
created some activities and milestone in the project. Let say one of the
milestone got pushed further to a new date and I want this change to get
updated to a field in excel where additional calculations are performed. Can
I achieve this process of updating fields? If so, can somebody tell me the
way to do it? Thanks
KT
I am trying to find out the option of linking Microsoft Project and Excel. I
created some activities and milestone in the project. Let say one of the
milestone got pushed further to a new date and I want this change to get
updated to a field in excel where additional calculations are performed. Can
I achieve this process of updating fields? If so, can somebody tell me the
way to do it? Thanks
KT