Hi BarbHenderson,
What invoiced values? Work? Cost? Work values can be entered in Actual
Work. To enter Actual Cost data, you will need to disable "Actual costs
are always calculated by Microsoft Project" on the Calculation tab of
the Tools > Options dialog box.
I hope this helps. Let us know how you get along.
Julie