Is it possible to approve a resource only for a specified amt of w

M

Moses Bunting

for example, I want to approve a project mgr to use 40 hours of a enterprise
resource, i.e. he is not allowed to use more than 40 hours. Everything we've
seen shows us that once a resource is added to the project, the project
manager has carte blanche to assign them to whatever tasks they deem
necessary.

I understand this could be controlled through task delegation, but in our
organization, we always have situations where tasks must be delegated to more
than one resource.

Thank you.
 
D

Dale Howard [MVP]

Moses --

You will need to establish a project management process to handle this
situation. There is no default method within Project Server to limit the
amount of work that a project manager can assign to a team member. Sorry.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top