L
LJI
I'd like to be able to get the Summary Progress date value for
use in an equation to return a progress to schedule.
A simple example:
A summary task : BL Finish = 8/30/06 Start 7/10/06 Finish 9/7/06
Tracking Gantt -> Summary Progress date = 8/3/06 (35% cmplt)
If I check the status of this task on 8/15/05 - the progress is 12 days
behind schedule! While the Finish Varaince is only 5days.
The 12days is the value I'm trying to capture.
Is there a way to obtain the SUMMARY PROGRESS DATE in an equation?
use in an equation to return a progress to schedule.
A simple example:
A summary task : BL Finish = 8/30/06 Start 7/10/06 Finish 9/7/06
Tracking Gantt -> Summary Progress date = 8/3/06 (35% cmplt)
If I check the status of this task on 8/15/05 - the progress is 12 days
behind schedule! While the Finish Varaince is only 5days.
The 12days is the value I'm trying to capture.
Is there a way to obtain the SUMMARY PROGRESS DATE in an equation?