Is there a way to obtain the Summary Progress Date?

L

LJI

I'd like to be able to get the Summary Progress date value for
use in an equation to return a progress to schedule.

A simple example:
A summary task : BL Finish = 8/30/06 Start 7/10/06 Finish 9/7/06
Tracking Gantt -> Summary Progress date = 8/3/06 (35% cmplt)

If I check the status of this task on 8/15/05 - the progress is 12 days
behind schedule! While the Finish Varaince is only 5days.

The 12days is the value I'm trying to capture.

Is there a way to obtain the SUMMARY PROGRESS DATE in an equation?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top