P
PMadm
Can someone tell me how to complete a task assigned to a generic resource when generics do not have/use timesheets? Am using Project Server 2003 and MS Proj Pro 2003 environment. Generic resources are defined in resource pool to represent external contracted agents. Want to mark task assigned to the generic resource complete! Have tried LOTS of methods to complete the task: Entering actual hours = work (this is overwritten by protected actuals because these do not actually exist for generic resources), entering % complete = 100% (as soon as syncronize with actuals its reset), entering physical % complete = 100% (does not show task as complete), changing remaining work to 0 (doesnt' stick...). Prefer not to change task to milestone, i.e., 0 work, as that affects start and finish dates unless I force them
It could be this is a FLAW IN LOGIC related to actuals and protected actuals for generic resources... It should not be checking protected actuals for generic resouces!
It could be this is a FLAW IN LOGIC related to actuals and protected actuals for generic resources... It should not be checking protected actuals for generic resouces!