Issue with saveing project to Project Server

C

Chris

Morning All,

I am having to call upon your expertise once again. I will keep this
problem high level.

When a plan is created outside the Project Server, the end date and the
leveling process is correct. If you click level project, the little bar in
the bottom will click a few bars every few seconds. Everything works out
great.

But when you take the plan to the server it will ask you to replace the
resouces with people that match in our resource pool's whos ids are pulled
from Active Directory. I will click yes, then it will take all of the
leveling out of the plan. MS Project will decided that everyone can work
30-40 hours in each day that they are assigned to a task.

It seems it is stacking the tasks with the same start dates and not leveling
them like it should, when I click level project I do clear out the prior
leveling and it will be level in less than a second but the dates will not
change to the correct date.

Any help?

Thanks
CHris
 
M

Mike Glen

Hi Chris,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP



Morning All,

I am having to call upon your expertise once again. I will keep this
problem high level.

When a plan is created outside the Project Server, the end date and
the leveling process is correct. If you click level project, the
little bar in the bottom will click a few bars every few seconds.
Everything works out great.

But when you take the plan to the server it will ask you to replace
the resouces with people that match in our resource pool's whos ids
are pulled from Active Directory. I will click yes, then it will
take all of the leveling out of the plan. MS Project will decided
that everyone can work 30-40 hours in each day that they are assigned
to a task.

It seems it is stacking the tasks with the same start dates and not
leveling them like it should, when I click level project I do clear
out the prior leveling and it will be level in less than a second but
the dates will not change to the correct date.

Any help?

Thanks
CHrisHi ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.
 