timbobd
I have a project with defined tasks and related level-of-effort estimates in
hours. I have manually created a leveled and optimized plan in Excel and want
to enter this plan into Project 2007.
I entered all tasks with LOEs as "work" hours as well as specific
dependencies but am having problems when assigning resources. Basically I
just want to assign the tasks and have Project schedule them at the earliest
time without overallocations. However, Project is overallocating. For
example, a task with no dependencies may be moved to start on the project
start date even though the resource already has 40 hours for the first week -
I thought that I read that tasks with type "Fixed Units" would not allow
overtime.
Any tips or hints on how to do this? So far I am slowly entering one task at
a time and manually correcting errors. This is very time consuming and
pain-staking. FYI I am not using resource leveling due to past experience and
warning from fellow project managers.
Thanks in advance!
Tim D
hours. I have manually created a leveled and optimized plan in Excel and want
to enter this plan into Project 2007.
I entered all tasks with LOEs as "work" hours as well as specific
dependencies but am having problems when assigning resources. Basically I
just want to assign the tasks and have Project schedule them at the earliest
time without overallocations. However, Project is overallocating. For
example, a task with no dependencies may be moved to start on the project
start date even though the resource already has 40 hours for the first week -
I thought that I read that tasks with type "Fixed Units" would not allow
overtime.
Any tips or hints on how to do this? So far I am slowly entering one task at
a time and manually correcting errors. This is very time consuming and
pain-staking. FYI I am not using resource leveling due to past experience and
warning from fellow project managers.
Thanks in advance!
Tim D