S
Scott Morrissey
Does anyone know how to set up a task assignment that would keep the
spread of remaining hours per week constant as actual time is posted
against it and to keep the start and end dates constant. For example,
"Jim" is scheduled to work 5 hours per week on a support task on
average until the end of the year. Jim may only post 1 hour one week
and 7 hours the next. The tool seems to always re-allocate the 5
remaining hours per week to something else AND the Finish date
changes. Is there a combination of settings we could establish that
would cause the update process to react the way we want it (kep the
finish day the same and keep remaining hours spread at 5 hours per
week)?
spread of remaining hours per week constant as actual time is posted
against it and to keep the start and end dates constant. For example,
"Jim" is scheduled to work 5 hours per week on a support task on
average until the end of the year. Jim may only post 1 hour one week
and 7 hours the next. The tool seems to always re-allocate the 5
remaining hours per week to something else AND the Finish date
changes. Is there a combination of settings we could establish that
would cause the update process to react the way we want it (kep the
finish day the same and keep remaining hours spread at 5 hours per
week)?