C
Cleo
The resource calendar has the 8 hr workday and 5 day work week. I'm
not sure where the issue is. Can someone help?
not sure where the issue is. Can someone help?
I changed it so I should see a difference. Thank you!Hi Cleo,
Welcome to this Microsoft Project newsgroup
Tools/Options/Schedule tab and Duration is enterd in: to Hours.
FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
Seehttp://tinyurl.com/2xbhcfor Project Tutorials
- Show quoted text -
Hi Cleo,
Welcome to this Microsoft Project newsgroup
Tools/Options/Schedule tab and Duration is enterd in: to Hours.
FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
Seehttp://tinyurl.com/2xbhcfor Project Tutorials
- Show quoted text -
Hi Cleo,
I didn't realise I was on the server newsgroup when I answered thisI
shouldn't have answered as I don't have a server, so if this is related to
the use of a server, I hope someone else will step in. In a stand-alone
project what you are saying is, indeed impossible! I don't understand your
situation. Do you mean you have 6 days of work (48 hours) assigned to you
in a single day? If so, you are overallocated and need to resource level.
Project will do this for you via Tools/Resource levelling, whence Project
will delay tasks until you are available to work on them.
Mike Glen
Project MVP
- Show quoted text -