KL: My time per day is in days instead of hours. How do I correct forthis?

C

Cleo

The resource calendar has the 8 hr workday and 5 day work week. I'm
not sure where the issue is. Can someone help?
 
M

Mike Glen

Hi Cleo,

Welcome to this Microsoft Project newsgroup :)

Tools/Options/Schedule tab and Duration is enterd in: to Hours.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
C

Cleo

Hi Cleo,

Welcome to this Microsoft Project newsgroup :)

Tools/Options/Schedule tab and Duration is enterd in: to Hours.

FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm
I changed it so I should see a difference. Thank you!
Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
Seehttp://tinyurl.com/2xbhcfor Project Tutorials




- Show quoted text -

Thanks for sending that. I had one in hours and the other in days. I
hope it fixes it! :)
 
C

Cleo

Hi Cleo,

Welcome to this Microsoft Project newsgroup :)

Tools/Options/Schedule tab and Duration is enterd in: to Hours.

FAQs, companion products and other useful Project information can be seen at
this web address:http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
Seehttp://tinyurl.com/2xbhcfor Project Tutorials




- Show quoted text -

What I failed to make clear is that i.e. I have 6 days in 1 day which
isn't possible. 48 hours in one day is impossible.
 
M

Mike Glen

Hi Cleo,

I didn't realise I was on the server newsgroup when I answered this :( I
shouldn't have answered as I don't have a server, so if this is related to
the use of a server, I hope someone else will step in. In a stand-alone
project what you are saying is, indeed impossible! I don't understand your
situation. Do you mean you have 6 days of work (48 hours) assigned to you
in a single day? If so, you are overallocated and need to resource level.
Project will do this for you via Tools/Resource levelling, whence Project
will delay tasks until you are available to work on them.

Mike Glen
Project MVP
 
C

Cleo

Hi Cleo,

I didn't realise I was on the server newsgroup when I answered this :( I
shouldn't have answered as I don't have a server, so if this is related to
the use of a server, I hope someone else will step in. In a stand-alone
project what you are saying is, indeed impossible! I don't understand your
situation. Do you mean you have 6 days of work (48 hours) assigned to you
in a single day? If so, you are overallocated and need to resource level.
Project will do this for you via Tools/Resource levelling, whence Project
will delay tasks until you are available to work on them.

Mike Glen
Project MVP






- Show quoted text -

The resource graph from within Assign Resources show overallocations
from 2.5 days in one day to 6 days in one day. They showing having
worked this time and have time planned this way. Sounds like I need to
go into each project plan and scale down hours but I'm not sure how
since some of these tasks take weeks at a time. So I need some help
figuring this out. Thanks for your help though.
 
M

Mike Glen

You're welcome, Cleo, I'm sorry I can't help further, as without a server, I
don't recognise "within Assign Resources", which I presume is some sort of
view. If nobody jumps in to help, I suggest we end this thread and you
could try posting a new one.:)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
Top