Labor vs Material resources

J

Jeff

Has anyone every figured out how to display labor and material resources
separately for summary tasks? Please read this several times to make sure
you understand what I am asking before you respond. I actually do not think
this is possible in Project (which is nuts - this seems so basic), but maybe
someone has found a way to do this.

Thanks!
 
J

Jan De Messemaeker

Hi,

Task Usage View
Create a group as follows

Group By Outline Number Task Ascending
Then By Resource Type Assignment Ascending

Check on Group Assignments, not tasks
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620