Lag time between Start-Date and Finish-Date

S

Shahriar N k

Is it possible to add lag time between Start and Finish date of a single task?
(I know its possibe to add lag time between 2 tasks that are linked)

Thanks in advance.
 
S

Shahriar Nour Khondokar

I will provide a little more clarification:
Consider 1 single task T of Work = 8hrs, Resource = 100%, hence Duration =
8hrs.
So, if T starts on 03/29 it will finish on 03/29. But i want T to finish on
03/30 with out affecting Work or Resource%.
Do you think that is possible?
Thanks.
 
J

Jan De Messemaeker

Hi,

Well, it's not easy, and I don't understand the relevance but yes, it is
feasible
Make the duration 2 days: work jumps to 16 hrs
Task Usage View, change bottom tier of timescale to hours
Enter 0 for work during the "interruption" hours until total work becomes
the original 8 hrs.
There you are.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
M

Mike Glen

Hi Shahriar ,

Welcome to this Microsoft Project newsgroup :)

It sounds to me as if you want to split the task leaving a gap in between.
Click the split button on the toolbar, move the cursor to the point you want
to split the bar, then click and drag to the right. Alternatively, in the
Task Usage view, enter zeros on the days you want the lag.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
S

Steve House [MVP]

You can split the task using the "Spit Task" tool on the toolbar. That
would be the equivalent to adding lag time since a split task begins and
procedes for a period of time, then stands down with work stopping for a
while, and then resumes so work can again procede. You can split the task
as many times as you need. Note that when you do, the suration number
doesnt change because time within the split is considered non-worknig time
and so isn't counted in the duration. If you have a task that runs the
first two weeks in February and split it by a week, the task will now finish
3 weeks after it starts however its duration will remain at 2 weeks.

HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top