Latest Skinny on Cost Resources

A

Andrew Lavinsky

Last I checked (about a year ago), the use of Cost Resources wasn't
recommended due to issues with multiple assignments and timephased cost data.

Curious if that's still the general opinion, or if anyone's started using
them extensively without those issues - specifically to create a timephased
budget?

Note that I am not talking about Budget Cost Resources, but Cost Resources
applied to tasks.

Thanks in advance.
 
R

Rod Gill

From memory, the "only" issue is when using Cost Resources on a Task with
one or more Work Resources and updating from Project Server. If you are not
connected to Project Server or are not updating from My Tasks then you
should be OK.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Andrew Lavinsky said:
Last I checked (about a year ago), the use of Cost Resources wasn't
recommended due to issues with multiple assignments and timephased cost
data.

Curious if that's still the general opinion, or if anyone's started using
them extensively without those issues - specifically to create a
timephased
budget?

Note that I am not talking about Budget Cost Resources, but Cost Resources
applied to tasks.

Thanks in advance.

__________ Information from ESET Smart Security, version of virus
signature database 4791 (20100120) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4791 (20100120) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
A

Andrew Lavinsky

As I recall, there was an issue where if you edit the timephased costs in the
Resource/Task Usage Views, the numbers wouldn't add up correctly....or the
totals would get corrupted or something like that.
 
A

Andrew Lavinsky

That helped - so the issues/feature quirks with Project Server then are still
existing....at least as of the Post-SP1 IU. I am still a bit hesitant to
chalk that many usage restrictions up to simple training issues.

- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
J

JulieS

Hi Andrew,

To the best of my knowledge, the advice on usage is still in effect.

Julie
 
D

Dale Howard [MVP]

Andrew and Julie --

Talking with some folks at Microsoft recently, I believe this usage
recommendation continues with Project Server 2010 as well. Hope this helps.
 