Level Resources : Project Server 2007

A

Alain

Hello,

If I need to level resource on a project because I have some resource
conflicts, I can use the function "Level Resources". Does this function take
into account the workload of the resource for the project I am working with
or also for all other projects (stored in Project Server) where the resources
is assigned ?

Thanks.
 
B

Ben Jardine

Hi Alain,

My experience of beta 2 says "yes" if you have access to those projects.

However, it seems that project can only alter tasks that you have open in
the MS Project client - therefore only tasks in open projects will move,
regardless of priority.
 