leveling a resource's time across projects

S

Session

Hello,
I'm looking to setup a resource so that when he is leveled, he works equally
across 3 tasks to add up to 8 hrs a day. It seems as though MS Project
forces the projects to be stacked one after another because it wants to
allocate the max units of a resource that it can in a single day. Is there a
way to have leveling do what I'm looking for?

Thanks,
Session
 
J

Jim Aksel

Consider changing the resource allocation units to 33% on each of the three
tasks in question
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top