Leveling on different projects

J

J.Kümpel

H

I'm currently running 4 big projects on a Project Server 2003 and Project Pro 2003

Leveling settings are: Day by Day - Clear before leveling - All project - Priority, Standard - Level resources with proposed booking type

My problem is When I’m leveling projects and 2 task occur on the same day. Let say the 12/12-2003
Task 1 on project A is set to 1 Hour Work and duration with resource X
Task 2 on project B is set to 8 hours Work and duration with resource X
When I level projects moves task 2 to start right behind task one. But the trouble here is that project B is another customer and in a whole other town

How do I handle this?
Can I setup up somewhere that task on different projects can't occur on the same day?
Regards
Jesper
 