Leveling Resources without screwing up Timeline

D

Dasani

Hi,

If anyone can help me. I'm using MS Project 2002 and trying to level
resources without messing up the timeline. Can anyone give me advice
on doing so?


Thanks
 
D

Dale Howard [MVP]

Dasani --

When you use Microsoft's built-in leveling tool, the software levels in two
days: (1) delaying tasks and (2) splitting tasks. As you might surmise,
both of these results will change the schedule of the project and will
impact your planned timeline for the project. If this is not an acceptable
result, you can use one of several manual approaches to leveling, such as
replacing overallocated resources with available resources. Hope this
helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
D

Dasani

Hi Dale,

What are your thoughts on using:

Tools / Level resources... / Level only within available slack / Level now

D
 