D
Dave
I have a resource who is free for the week Oct 5th - 12th. I have tasks in
my plan taking 2 days, 2.5 days, 2 days. Allocation units for this resource
is set at 40% so the actual work is less than that. These tasks have one
dependency which is already complete.
When I level resources, these tasks are pushed out to late October/early
November.
Analysing using "View Resource Availability" in PWA shows that this resource
has 1 task for another project on the 17th and 20th Octobver but nothing
else. I.e. 21st-24th Oct and 6-10th Oct free. Why won't project fill in
these days when I level?
This is driving me nuts.
Dave
my plan taking 2 days, 2.5 days, 2 days. Allocation units for this resource
is set at 40% so the actual work is less than that. These tasks have one
dependency which is already complete.
When I level resources, these tasks are pushed out to late October/early
November.
Analysing using "View Resource Availability" in PWA shows that this resource
has 1 task for another project on the 17th and 20th Octobver but nothing
else. I.e. 21st-24th Oct and 6-10th Oct free. Why won't project fill in
these days when I level?
This is driving me nuts.
Dave