S
STEVO
Dear All,
I would really like to get some clarification on the following
question.
When you level a project, does it level taking into consideration
resource assignments across other projects?
I have asked this question before, and I was told that the answer is
"yes, but you must have all projects open" Although hard to believe i
accepted this answer as final, but i have just created 2 test projects
(A&B), assigned identical resources from the global resource pool, and
then allocated the same resources to each task on both A&B projects. I
have now closed Test Project A, and when i run levelling on Project B
sure enough it levels the resource tasks taking other project resource
allocations into consideration, which goes against the original answer
I recieveed.
grateful for any feedback or advice on this
Regards
Steve
I would really like to get some clarification on the following
question.
When you level a project, does it level taking into consideration
resource assignments across other projects?
I have asked this question before, and I was told that the answer is
"yes, but you must have all projects open" Although hard to believe i
accepted this answer as final, but i have just created 2 test projects
(A&B), assigned identical resources from the global resource pool, and
then allocated the same resources to each task on both A&B projects. I
have now closed Test Project A, and when i run levelling on Project B
sure enough it levels the resource tasks taking other project resource
allocations into consideration, which goes against the original answer
I recieveed.
grateful for any feedback or advice on this
Regards
Steve