N
Neil Ratcliffe
Hi,
We are just in the process of rolling out Project 2002 EPM to a fairly large
number of Porject Managers.
One area of feedback I have had from some of my Project managers (users of
Project 2000 in the past) is that in Porject 2002 they are unable to view
Resource Overallocation just within their project, therefore it makes it
very difficult to balance workload when considering only the project tasks
for that project manager.
Does anyone have a suggestion for how to view this kind of data taking into
account the alloacations for just the current project.
Also is there any way of levelling just a selected group of tasks ?
Thanks
Neil
We are just in the process of rolling out Project 2002 EPM to a fairly large
number of Porject Managers.
One area of feedback I have had from some of my Project managers (users of
Project 2000 in the past) is that in Porject 2002 they are unable to view
Resource Overallocation just within their project, therefore it makes it
very difficult to balance workload when considering only the project tasks
for that project manager.
Does anyone have a suggestion for how to view this kind of data taking into
account the alloacations for just the current project.
Also is there any way of levelling just a selected group of tasks ?
Thanks
Neil