Levelling & Status Date

S

Steve

Hi,

Having statused my plan (... and the plan is a little ahead of schedule!) I
then level it to put non-started tasks to the status date.

But some non-started tasks previously scheduled on or after the status date
were scheduled BEFORE the status date after levelling. Strange isn't it?

Can you help?

Thanks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top