On the formula how do have it calculate based on 365 days ??
Roger Govier said:Hi Luis
Yes, I understand that, but if you change the order and use (TO DATE -
HIRE DATE) that will calculate the interval for you based upon 365 (or
366 in leap year) days.
With Hire date of 01 Jan 2005 and to date being 16 Sep 2006, the formula
=DAYS360(Hire date,To date) produces a result of 615
=(To Date-Hire date) produces a result of 623
You need to format the cell with the formula as
Format>Cells>Number>General otherwise you will see a result of
14/09/1901 (being 623 days after 01/01/1901)