Limit entries in resource list

A

assaf1978

Hi,
How do I limit the entries of resources to only from the list (which comes
from a resource pool) and don't enable entries that are keyed in manually?

Thanks,
Assaf.
 
J

Jan De Messemaeker

Hi,
Tools, Options, General, UNCHECK Automatically add new resoruces and tasks.
That will not make the entry impossible but at least it will give a warning.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620