D
Digman
Can anyone tell me if there is a limitation on the number of tasks that can
be assigned as predecessors to a single task (single task with multiple
predecessors)?
I am trying to import from MS-Access. I am finding that the predecessors
are being truncated (looks like 255 characters limit). I tried cutting and
pasting the predecessors in manually, but still seems to be truncating them.
I am trying to paste in 150 tasks as predecessors (4 characters per task
plus the comma). I am using MS-Project 2007.
The reason I have so many preds. is because I believe I should avoid using
Summary tasks as predecessors (this would reduce the amount considerably).
be assigned as predecessors to a single task (single task with multiple
predecessors)?
I am trying to import from MS-Access. I am finding that the predecessors
are being truncated (looks like 255 characters limit). I tried cutting and
pasting the predecessors in manually, but still seems to be truncating them.
I am trying to paste in 150 tasks as predecessors (4 characters per task
plus the comma). I am using MS-Project 2007.
The reason I have so many preds. is because I believe I should avoid using
Summary tasks as predecessors (this would reduce the amount considerably).