Limited by Outlook time period date ranges

S

ST

Trying to use Outlook to capture time (ie., hours per day) instead of using
My Timesheet and My Tasks in PWA 2007, but we may have a problem and would
like to check with the newsgroup.

Outlook does not seem to allow editing of time periods beyond a couple of
weeks or so from the planned dates of the assignments.

Is this normal? If so, then how would someone be able to enter a few
actuals hours against a task that they've just worked on which was scheduled
to start a few weeks later?

/Spiro Theopoulos.
 
M

Marc Soester [MVP]

You will either have to use PWA or need to custom develop a solution around
Outlook and Project Server to acheive your request.
sorry
 
G

Gary Chefetz

Well thanks Marc, but all we're doing here is reverting to a tried-and-true
2003 method.
 