S
SAbodo1
Is there a way within MS project to have multiple tasks set the finis
date based on resource allocation? I have tried using the followin
task for a test:
task A
Duration 14hrs
start date 3/25/09
Finish date (Calcualted)
resource Bob
Resource availbility 15%
and I have found that the first task assigned will recalculate based o
availability but subsequent tasks will revert to a 100% availability.
what I need is to take a resource that is assigned to multiple smal
tasks over a certain timeframe. For example Bob is assigned to (3)
hours tasks over a 2 week period with a 10% resource availbility
date based on resource allocation? I have tried using the followin
task for a test:
task A
Duration 14hrs
start date 3/25/09
Finish date (Calcualted)
resource Bob
Resource availbility 15%
and I have found that the first task assigned will recalculate based o
availability but subsequent tasks will revert to a 100% availability.
what I need is to take a resource that is assigned to multiple smal
tasks over a certain timeframe. For example Bob is assigned to (3)
hours tasks over a 2 week period with a 10% resource availbility