After a plan is imported, in PWA for views that show a
line zero, the line zero does not reflect the project name
but an alternative naming convension such as MSProj11.
Does anyone know why this is happening and how this can be
changed to reflect the actual project name?
 
D

Dale Howard [MVP]

Michelle --

Line 0 is known as the Project Summary Task. Click File - Properties and
set the Title value for the project. This information is displayed as the
Task Name for Line 0. Hope this helps.
 
M

Michelle

THanks! I think this did it.
-----Original Message-----
Michelle --

Line 0 is known as the Project Summary Task. Click File - Properties and
set the Title value for the project. This information is displayed as the
Task Name for Line 0. Hope this helps.







.
 