Link tasks from multiple, detailed projects into a master project

M

Mark Kyprianou

I currently have multiple detailed projects in separate project files. I
would like to create a master project that shows a collapsed project duration
for each of the individual projects.

How do I do this?

thanx in advance, mark
 
M

Mark Kyprianou

So if I update the project, do I have to remove and then re-insert it?
Basically, I would like to just update the detailed projects and have that
info flow into the global project. so I need to re-insert it?

thanx, mark
 
J

John

Mark Kyprianou said:
So if I update the project, do I have to remove and then re-insert it?
Basically, I would like to just update the detailed projects and have that
info flow into the global project. so I need to re-insert it?

thanx, mark

Mark,
No. Unless the default setting was changed when the master was built
(Insert/Project), the subprojects will automatically be dynamically
linked to the master and vice versa. Updating tasks in either will be
reflected in the other.

Hope this helps.
John
Project MVP
 