I have a plan built via MS Project (MS Project Server 2003) that links 8
plans together: this plans doesn't have any actual tasks, only linked plans.
This plan has never been published, only saved (and the published options
for saving have been disabled). In PWA, I see a task from one of the source
plans, and one for the plan that contains the 8 plans - duplicate tasks. I'm
confused - any ideas?

PK Consulting
 
J

John

PK Consulting said:
I have a plan built via MS Project (MS Project Server 2003) that links 8
plans together: this plans doesn't have any actual tasks, only linked plans.
This plan has never been published, only saved (and the published options
for saving have been disabled). In PWA, I see a task from one of the source
plans, and one for the plan that contains the 8 plans - duplicate tasks. I'm
confused - any ideas?

PK Consulting

PK,
You will probably get a better response if you re-post to our sister
newsgroup, microsoft.public.project.server. This newsgroup is dedicated
to the stand alone version of Project.

John