links

P

project newby

Hi there,

I was also wondering whether there was a way to highlight the links
from one task only. At the moment when I turn the lins on, all the
links appear, which is very confusing.

What I want to do is to click on a task and be able to see what are its
precedents/successors.

Thanks
 
G

Gérard Ducouret

Hello,
Use the Relationship Diagram : Views / More Views...
or the Task Form, with the Predecessors and Successors details:
Window / Split...
Select the task Form, then : Format / Details / Predecessors & Successors.

Gérard Ducouret
 
M

Mike Glen

Hi again project newby ,

You can't highlight the links. However, the predecessors column will give
you the ID of the predecessors, and you can Insert/Column and select
Successors to give that data.

Otherwise, if you go to Windows/Split, right-click in the lower pane and
select Predecessors and Successors, then click on a task it will show what
you want.

Alternatively, click in the lower pane, and then View/More Views.../and
select the Relationship Diagram, which will show the network diagram for the
selected task.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #, at this site: http://tinyurl.com/2xbhc or
this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 