Load summary resource assigments/other projects and commitmentsdetail

A

Alice Roman

Hi,
I'm an administrator, and I can see the detailed timeline tasks under
other projects and commitments, by each resource in the resource usage
view when I'm in PWA, no matter which project timeline I go into.
However the project mangers can only see the total hours for other
projects and commitments, but I'd like them to see the details too
without being an administrtor.

Do you know which permission I need to give them in order to see this?
Thanks
 
M

Marc Soester [MVP]

Hi Alice,

the reason why you can see the other project details and the project
managers cant is because of security. If you give the PM's access to the
projects, they will see the details of the other projects as well. Be aware,
if you give the PM's access to the other projects, they do have the abillity
to change the other project schedules too.
Hope this helps
 
N

nalices

Marc Soester said:
Hi Alice,

the reason why you can see the other project details and the project
managers cant is because of security. If you give the PM's access to the
projects, they will see the details of the other projects as well. Be aware,
if you give the PM's access to the other projects, they do have the abillity
to change the other project schedules too.
Hope this helps
 