Local Calendar Needs to be Deleted

R

RandyK

(MSPS 2003) Someone inadvertently added a local standard calendar to a
project schedule that uses the enterprise calendar in global. Now they both
appear in just that one project schedule. How can I delete the local
calendar completely to keep the PM from using it in error?
 
D

Dale Howard [MVP]

RandyK --

First of all, you need to disable the option on the Server Configuration
page in PWA that allows anyone to use local Base calendars. Then you can
open this person's project, click Tools - Organizer, click the Calendars
tab, select the calendar, and delete it. Hope this helps.
 
D

Dale Howard [MVP]

Randy --

Sounds like your system is going crazy. The permission you cite should
entirely stop any PM from adding a local calendar to a project. Beyond
this, I have no idea how it could have happened. Hope this helps.




RandyK said:
Hi Dale -

Thanks for the tip. I was able to delete the calendar from the project.
however, when I checked PWA, I have "Enable only Enterprise Features"
checked
and below that, the "Allow projects to use local base calendars" in not
selected. Am I missing something?
 
Top