I achieved this with a large time critical schedule. I needed to keep tidy
up and other follow on tasks off the critical path and have the critical
path show for critical areas only. To do this I:
1) Made sure all Tasks were driven by links. Any date constraints were
allowed fixed dates, but had to have a note explaining them.
2) Added a milestone 2 weeks later than the last task with a must start on
constraint. Now all tasks except the last were non-critical!
3) Added deadlines for all key deliverable milestones. This made those paths
critical if no slack and reduced slack to conform with the deadline.
This worked brilliantly. In fact I had a view with tasks with deadlines
filter applied and the Total Slack column inserted. Total slack for each
deliverable was copied to Excel for each week so the trend on total slack
could be clearly seen. Tasks with rapidly reducing total slack got more
resources, tasks with increasing total slack got less. Management were all
over this report like a rash every Monday!
--
Rod Gill
Microsoft MVP for Project -
http://www.project-systems.co.nz
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
rosebud86 said:
How can I have a task that starts on day one and ends at the project
completion, but I don't want that task to be on the critical path?
__________ Information from ESET Smart Security, version of virus
signature database 4986 (20100330) __________
The message was checked by ESET Smart Security.
http://www.eset.com
__________ Information from ESET Smart Security, version of virus signature database 4986 (20100330) __________
The message was checked by ESET Smart Security.
http://www.eset.com