S
Skip Wick
We have remote facilities connecting in through
RoadRunner. They are reporting 5 to 10 minutes to build
team from enterprise. We have approx 650 resources in the
pool. Is there any way to pre-filter resources based on
RBS or location (custom field) so they only download only
their resources? I read in "Implementing Enterprise
Portfolio Management..." page 270 that the system will
prompt me for prefilters when the selection exceeds 1000
resources. Can I change the 1000 to say 100 which will
always create prompts for prefilters and reduce wait times?
Thanks
RoadRunner. They are reporting 5 to 10 minutes to build
team from enterprise. We have approx 650 resources in the
pool. Is there any way to pre-filter resources based on
RBS or location (custom field) so they only download only
their resources? I read in "Implementing Enterprise
Portfolio Management..." page 270 that the system will
prompt me for prefilters when the selection exceeds 1000
resources. Can I change the 1000 to say 100 which will
always create prompts for prefilters and reduce wait times?
Thanks