Sage --
You DO NOT need to reset the Units value for each resource after updating
actuals into the Microsoft Project plan. Here's what you don't understand:
the Units value you see for each resource assigned to a task initially
represents the original Units value. After updating actuals, however, the
number represents the Peak Units for each task assignment, which is the
maximum percentage of a working day shown in either the Actual Work field or
the Remaining Work field over the life of the task. For example, I assign a
resource at 50% Units on a task. When reporting actuals, the resource
enters 6 hours of Actual Work during one of the days in the reporting
period. The 6 hours of Actual Work converts to a Peak Units value of 75%.
When you update the progress on the task, the system automatically changes
the Peak Units value for the task assignment to 75%, but continues to assign
the Remaining Work hours at 50% Units across the remainder of the task.
I don't know where you got the idea that you have to reset the Units value
back to its original value on each task, but I believe you are wasting a lot
of time doing so. Hope this helps.