Manage Organization link not available in PWA

B

begellk

Hello,

I've been going through previously posted comments about hiding deleted
tasks in the timesheet view in PWA and I've determined that in order to
correct this problem, I need to enable the "Hide" feature, only I
cannot seem to find the path that will allow me to do so. As the
Administrator, I for some reason do not have the Manage Organization
link from the Admin menu. Any suggestions as to how I get to Manage
Organization and furthermore, how I enable the Hide button so that it
is visible on the timesheets of our resources?

Any help would be appreciated.

Thanks!

Katie Begell
 
D

Dale Howard [MVP]

Katie --

In the future, please post your Project Server questions to the
microsoft.public.project.server newsgroup, as this newsgroup is going to
close down. To answer your question, complete the following steps:

1. Log into PWA with administrator permissions
2. Click Admin - Server configuration
3. In the features grid, scroll to the Tasks section
4. Set the Hide Task from Timesheet permission to Allow
5. Click the Save Changes button

Hope this helps.
 
Top