Mark as milestone

G

Glen Mettler

In the Task Information dialog box under the Advanced tab, I can check the
"Mark as Milestone" box to have a task displayed as a milestone on the Gantt
chart.
Problem is that it selects the start date. Is there a way to have it
default to the finish date?

TIA
Glen
 
M

Mike Glen

Hi Glen,

Other than inserting a constraint date, change the constraint to As Late As
Possible.

Try posting this on the server newsgroup, as this one is closing down!
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://www.mvps.org/project/.

Mike Glen
MS Project MVP
 
G

Gérard Ducouret

Hello Glen,

You can do that but it needs some work :
You have to create 2 different symbols (Format / Bar Styles) : one for each
kind of milestone : Duration = 0 and Duration > 0.
You have to create 2 Flag fields with formulas which test on "Milestone" and
on "Duration"
It's a little bit complicated to explain so that I prefer to send you this
little mpp file where you'll find everything.
Tell me if it helps !

Gérard Ducouret
 