AndyN
Hi All,
(using Project Server 2003)
The question:
If I have a milestone in a project, with 0 work and 0 duration, and I assign
that milestone to a resource, how can I mark that milestone as complete?
I want to assign that milestone to a resource so that it appears in their
outlook calendar upon publish. I try to mark it as 100% complete in Project
(i.e. through Task Information), but then I get issues in becoming "out of
sync with my protected actuals". Can I get around this? (I seem to be able to
say "No" to Syncing with actuals, but I get that message every time I open
the project)
Any help most appreciated
Thanks in advance,
AndyN
(using Project Server 2003)
The question:
If I have a milestone in a project, with 0 work and 0 duration, and I assign
that milestone to a resource, how can I mark that milestone as complete?
I want to assign that milestone to a resource so that it appears in their
outlook calendar upon publish. I try to mark it as 100% complete in Project
(i.e. through Task Information), but then I get issues in becoming "out of
sync with my protected actuals". Can I get around this? (I seem to be able to
say "No" to Syncing with actuals, but I get that message every time I open
the project)
Any help most appreciated
Thanks in advance,
AndyN