Mass change of Max Units

P

Philip Braun

Good morning,

We are using MS Project Server 2007 with SP2 and up to August 2010
CU. I have two questions that are related to each other.

First of all, does anyone have a good way to level under-allocated
resoruces. I know that the leveling tool levels over-allocated
resources, but we would like to level the under-allocated resources on
the project.

If we can do the first one, then we do not have to do this one, but
since it does not look like we can level under-allocated resoruces, is
there a way to change the max units for each resource with out having
to go in task by task.

Any suggestions would be very helpful here.

Thank you!
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top