J
Jurgen D
Hello
I've a question that's very simple but important for my project.
i have 4 subprojects and i have one master project with the 4
subprojects.
If i publish both subprojects and master project to the project server
2003
will there be a double calculation for the assignment??
I mean: I you assign a resource for 8 hours in a subproject and you
publish both sub and master project to the server will the resource
availability be accounted for 16 hours??
sorry for my english...
Greetings
I've a question that's very simple but important for my project.
i have 4 subprojects and i have one master project with the 4
subprojects.
If i publish both subprojects and master project to the project server
2003
will there be a double calculation for the assignment??
I mean: I you assign a resource for 8 hours in a subproject and you
publish both sub and master project to the server will the resource
availability be accounted for 16 hours??
sorry for my english...
Greetings