Master Project - dates are changed

S

Shyler

I have created several individual project files and combined into one Master
file with a resource pool. After I insert the projects into the master file
the dates for each of the individual projects change. I have verified that
my project calendars and definitions of the days are the same. I’ve also
ensured that I close each task down to a single line before inserting. There
must be something that I am missing but I just can't figure it out.
 
J

JulieS

Hello Shyler,

If you expand the inserted projects, do the dates change to what
they should be? It's very common to see incorrect dates until you
expand the subproject.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
S

Shyler

JulieS - thank you. It took me a while to figure it out but what was
happening is that the Project Start Date was wrong causing all my tasks to be
thrown off. Not sure why. But once I fixed that date my problem was fixed.
Appreciate your help.
 
J

JulieS

You're welcome Shyler and thanks for the feedback. I'm glad to know
you were able to resolve the problem.

Julie
 