L
LeslieF
Hello,
I'm using MSP Pro 2003 and project server 2003. I have a master file that
has approx 30 sub-projects. When I select all, then select Show all Subtasks,
I receive the following error:
An important error occurred.
Check row 0 column 116.
Well, I do know that row 0 is the project summary task and I've selected for
those to be show in the sub-projects. However, I don't have 116 columns in
any of the files. How can I zero in on this error?
Any help will be greatly appreciated!
....L
I'm using MSP Pro 2003 and project server 2003. I have a master file that
has approx 30 sub-projects. When I select all, then select Show all Subtasks,
I receive the following error:
An important error occurred.
Check row 0 column 116.
Well, I do know that row 0 is the project summary task and I've selected for
those to be show in the sub-projects. However, I don't have 116 columns in
any of the files. How can I zero in on this error?
Any help will be greatly appreciated!
....L