Master Project Graphical Indicators rolled up

S

Steve Scott

I have sub-project plans rolling up into a master plan. In teh sub-project
plans I have an autocalculated RAG column showing Finish variance using
Graphical Indicators. It would appear that I am unable to roll them up any
further to teh individual insertion point tasks in teh Master Plan - is this
correct?
 
J

Jim Aksel

Apply the same formula to the field in the master project. It should roll up
for you nicely.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
Top